QUANTITIES OF MATERIALS PER CUBIC METRE OF CONCRETE
Quantity of materials such as cement, sand, coarse aggregates and water required per cubic meter of concrete and mortar varies with the mix design of the concrete and mortar respectively. Following table gives the estimated quantity of materials required per cubic meter of mortar and concrete for various nominal mixes.
Quantity of materials such as cement, sand, coarse aggregates and water required per cubic meter of concrete and mortar varies with the mix design of the concrete and mortar respectively. Following table gives the estimated quantity of materials required per cubic meter of mortar and concrete for various nominal mixes.
NOMINAL MIX
|
WATER CEMENT RATIO
|
WATER PER 50KG BAG OF CEMENT
|
CEMENT
|
SAND (CUM)
|
CRUSHED STONES (CUM)
| |||
CEMENT
|
F.A.
|
C.A.
|
BY WEIGHT (KG)
|
BY NUMBER OF BAGS
| ||||
1
|
1
|
–
|
0.25
|
12.5
|
1015
|
20.3
|
0.710
|
–
|
1
|
1.5
|
0.28
|
14
|
815
|
16.3
|
0.855
|
–
| |
1
|
2
|
–
|
0.3
|
15
|
687
|
13.74
|
0.963
|
–
|
1
|
2.5
|
–
|
0.35
|
17.5
|
585
|
11.7
|
1.023
| |
1
|
3
|
–
|
0.4
|
20
|
505
|
10.1
|
1.06
|
–
|
1
|
4
|
–
|
0.53
|
26.5
|
395
|
7.9
|
1.106
|
–
|
1
|
6
|
–
|
0.7
|
35
|
285
|
5.7
|
1.197
|
–
|
1
|
8
|
–
|
0.9
|
45
|
220
|
4.4
|
1.232
|
–
|
1
|
1
|
2
|
0.3
|
15
|
560
|
11.2
|
0.392
|
0.784
|
1
|
2
|
2
|
0.42
|
21
|
430
|
8.6
|
0.602
|
0.602
|
1
|
1.5
|
3
|
0.42
|
21
|
395
|
7.9
|
0.414
|
0.828
|
1
|
1.66
|
3.33
|
0.48
|
24
|
363
|
7.26
|
0.419
|
0.838
|
1
|
2
|
3
|
0.5
|
25
|
385
|
7.7
|
0.539
|
0.808
|
1
|
2
|
3.5
|
0.53
|
26.5
|
330
|
6.6
|
0.462
|
0.808
|
1
|
2
|
4
|
0.55
|
27.5
|
310
|
6.2
|
0.434
|
0.868
|
1
|
2.5
|
3.5
|
0.57
|
28.5
|
305
|
6.1
|
0.534
|
0.748
|
1
|
2.5
|
4
|
0.6
|
30
|
285
|
5.7
|
0.499
|
0.798
|
1
|
3
|
4
|
0.65
|
32.5
|
265
|
5.3
|
0.556
|
0.742
|
1
|
2.5
|
5
|
0.65
|
32.5
|
255
|
5.1
|
0.446
|
0.892
|
1
|
3
|
5
|
0.69
|
34.5
|
240
|
4.8
|
0.504
|
0.84
|
1
|
3
|
6
|
0.75
|
37.5
|
215
|
4.3
|
0.452
|
0.904
|
1
|
4
|
8
|
0.95
|
47.5
|
165
|
3.3
|
0.462
|
0.924
|
Notes:
1. F.A.= Fine Aggregates, C.A.= Coarse Aggregates
2. The table is based on assumption that the voids in sand and crushed stone are 40 and 45 percent respectively.
3. Air content of 1 percent has been assumed.
4. For gravel aggregates decrease cement by 5 percent, increase sand by 2 percent and coarse aggregate in proportion to fine aggregate in mix.
4. No allowance has been made in the table for bulking of sand and wastage.